A and B can separately make a wall in 10 days and 15 days respectively. How many days before completion should B leave the work so that the wall is finished in a total of 8 days?

  1. 9 days
  2. 10 days
  3. 8 days
  4. 5 days
Answer (Detailed Solution Below)
Option 4 : 5 days

Detailed Solution

Concept approach

Total = 30; A = 3, B = 2. A works all 8 days = 24

⇒ B does 6

⇒ B works 3 days

⇒ leaves 8 − 3 = 5 days before

Ultra Calci trickLCM work / efficiency

LCM 30

⇒ A 3/day, B 2/day. A works all 8 days = 24

⇒ B does 30 − 24 = 6

B works 6/2 = 3 days

⇒ leaves 8 − 3 = 5 days before completion ✓