A and B can separately finish a work in 15 and 20 days, respectively. A starts the work and B joins him from the fifth day. How much time will it take to finish the complete work?

(SSC Selection Post 2022 (Graduate, 5 Aug, Shift 3))
  1. 10²⁄₇ days
  2. 11³⁄₇ days
  3. 11 days
  4. 10 days
Answer (Detailed Solution Below)
Option 1 : 10²⁄₇ days

Detailed Solution

Concept approach

Work = LCM(15, 20) = 60; A = 4/day, B = 3/day

First 4 days A alone = 16

⇒ left 44 at 7/day = 6²⁄₇ days

Total = 4 + 6²⁄₇

⇒ 10²⁄₇ days