If 5 workers can complete a work in 18 days, how many workers are needed to complete the same work in 10 days?

(SSC Selection Post 2026 (Matric, 22 Sep, Shift 3))
  1. 9 workers
  2. 5 workers
  3. 6 workers
  4. 7 workers
Answer (Detailed Solution Below)
Option 1 : 9 workers

Detailed Solution

Concept approach

5×18 = 90 worker-days; 90/10 = 9 workers