P, Q and R, when working individually, can complete a job in 36 days, 48 days and 144 days respectively. P, Q and R start working together. P leaves the work 12 days before its completion, and Q leaves the work 8 days before completion. R works from the beginning till the end of the job. Determine the total number of days taken to complete the work.
(SSC CPO 2023)
- 27
- 30
- 25
- 24
Answer (Detailed Solution Below)
Option 1 : 27
Detailed Solution
Concept approach
Work = 144: P = 4, Q = 3, R = 1
⇒ 4(T − 12) + 3(T − 8) + T = 144
⇒ 8T = 216
⇒ T = 27 days
Ultra Calci trickLCM work
LCM 144: P = 4, Q = 3, R = 1 per day, total work 144; T = total days → R works T, Q works T − 8, P works T − 12
4(T − 12) + 3(T − 8) + T = 144 → 8T = 144 + 72 = 216
T = 216/8 = 27
⇒ 30 ✗ 25 ✗ 24 ✗
⇒ 27 ✓
P, Q और R, जब अलग-अलग कार्य करते हैं, तो किसी कार्य को क्रमशः 36 दिन, 48 दिन और 144 दिन में पूरा कर सकते हैं। P, Q और R एकसाथ मिलकर कार्य करना शुरू करते हैं। P कार्य पूरा होने से 12 दिन पहले कार्य छोड़ देता है, और Q कार्य पूरा होने से 8 दिन पहले कार्य छोड़ देता है। R कार्य के आरंभ से अंत तक कार्य करता है। कार्य पूरा करने में लगने वाले दिनों की कुल संख्या ज्ञात करें।
(SSC CPO 2023)
- 27
- 30
- 25
- 24
उत्तर (विस्तृत हल नीचे)
विकल्प 1 : 27
विस्तृत हल
कॉन्सेप्ट से हल
कार्य = 144: P = 4, Q = 3, R = 1
⇒ 8T − 72 = 144
⇒ T = 27 दिन
अल्ट्रा कैलसी ट्रिकLCM work
LCM 144: P = 4, Q = 3, R = 1 प्रतिदिन, कुल कार्य 144; कुल दिन T → R: T, Q: T − 8, P: T − 12 दिन
4(T − 12) + 3(T − 8) + T = 144 → 8T = 144 + 72 = 216
T = 216/8 = 27
⇒ 30 ✗ 25 ✗ 24 ✗
⇒ 27 ✓