A alone can do a work in 11 days, B in 22 days and C in 33 days. Day 1: A and B work; Day 2: B and C; Day 3: C and A; Day 4: A and B, and so on. In how many days will the work be completed?

(SSC CGL Mains 2021 (08.08.2022))
  1. 3 days
  2. 12 days
  3. 6 days
  4. 9 days
Answer (Detailed Solution Below)
Option 4 : 9 days

Detailed Solution

Concept approach

Work 66: A = 6, B = 3, C = 2

⇒ AB = 9, BC = 5, CA = 8

⇒ 3 days = 22

⇒ 9 days = 66

Ultra Calci trickLCM work

LCM 66 → A = 6, B = 3, C = 2 per day

Day 1: A + B = 9, Day 2: B + C = 5, Day 3: C + A = 8 → 3 days = 22

66 ÷ 22 = 3 cycles

⇒ 9 days