A can do a certain work in 12 days and B can do it in 18 days. They worked together for 4 days. The remaining work was completed by C alone in 6 days. If they get Rs 3,240 for the whole work, then the share of C in this amount will be:

(SSC MTS 2021)
  1. Rs 1,260
  2. Rs 1,170
  3. Rs 1,440
  4. Rs 1,000
Answer (Detailed Solution Below)
Option 3 : Rs 1,440

Detailed Solution

Concept approach

4 days: 4/12 + 4/18 = 5/9

⇒ C did 4/9

⇒ 4/9 × 3240 = Rs 1,440

Ultra Calci trickfraction line

A + B in 4 days = 4(1/12 + 1/18) = 4 × 5/36 = 5/9

⇒ C did 4/9

C's share = 3240 × 4/9 = 360 × 4

1,260 ✗ 1,170 ✗ 1,000 ✗

⇒ Rs 1,440 ✓