12 men can complete a painting work in 8 days, while 16 women can complete it in 12 days. 8 men started painting; after 6 days, 2 men were replaced by 4 women. How many days will they take to complete the remaining painting?

(SSC MTS 2020)
  1. 4
  2. 5
  3. 6
  4. 8
Answer (Detailed Solution Below)
Option 3 : 6

Detailed Solution

Concept approach

96 man-days = 192 woman-days

⇒ m = 2w. 8 men × 6 days = 48

⇒ remaining 48 man-days = 96 woman-days; 6m + 4w = 16w

⇒ 6 days