A certain number of persons can complete a work in 34 days working 9 h a day. If the number of persons is decreased by 40%, then how many hours a day should the remaining persons work to complete the work in 51 days?

(SSC CGL Mains 2018 (Sep 2019))
  1. 12
  2. 8
  3. 9
  4. 10
Answer (Detailed Solution Below)
Option 4 : 10

Detailed Solution

Concept approach

Persons × days × hours = const: M × 34 × 9 = 0.6M × 51 × h

h = 306/30.6 = 10 hours