A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 4 days B had to leave. Then A working with a new worker C completed the remaining work in 3 days. If C works alone, in how many days can he do 40% of the same work?
(SSC CGL 16/08/2021 (Shift-2))
- 9
- 10
- 8
- 8.5
Answer (Detailed Solution Below)
Option 1 : 9
Detailed Solution
Concept approach
A worked 4 + 3 = 7 days = 7/15; B worked 4 days = 4/10 = 6/15
⇒ together 13/15
⇒ C did 2/15 in 3 days
⇒ 40% = 2/5 = 6/15
⇒ 3 × 3 = 9 days
Ultra Calci trickLCM work
LCM 30: A = 2, B = 3
⇒ 4 days × 5 = 20
⇒ left 10 in 3 days with A + C
2 + C = 10/3
⇒ C = 4/3 per day; 40% of 30 = 12
⇒ 12 ÷ 4/3 = 9
10 ✗ 8 ✗ 8.5 ✗
⇒ 9 days
A और B किसी कार्य को क्रमशः 15 दिनों और 10 दिनों में पूरा कर सकते हैं। वे एक साथ कार्य करना शुरू करते हैं, लेकिन 4 दिन बाद B कार्य छोड़ देता है। फिर A नए कामगार C के साथ कार्य करते हुए शेष कार्य को 3 दिन में पूरा करता है। यदि C अकेले कार्य करता है, तो वह उसी कार्य के 40% भाग को कितने दिनों में पूरा कर सकता है?
(SSC CGL 16/08/2021 (Shift-2))
- 9
- 10
- 8
- 8.5
उत्तर (विस्तृत हल नीचे)
विकल्प 1 : 9
विस्तृत हल
कॉन्सेप्ट से हल
A ने 4 + 3 = 7 दिन = 7/15, B ने 4/10 = 6/15
⇒ कुल 13/15
⇒ C ने 2/15 (3 दिन)
⇒ 40% = 2/5 = 6/15
⇒ 9 दिन
अल्ट्रा कैलसी ट्रिकLCM work
LCM 30: A = 2, B = 3
⇒ 4 दिन × 5 = 20
⇒ शेष 10, 3 दिन में A + C से
2 + C = 10/3
⇒ C = 4/3 प्रति दिन; 30 का 40% = 12
⇒ 12 ÷ 4/3 = 9
10 ✗ 8 ✗ 8.5 ✗
⇒ 9 दिन
ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →