A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 4 days B had to leave. Then A working with a new worker C completed the remaining work in 3 days. If C works alone, in how many days can he do 40% of the same work?

(SSC CGL 16/08/2021 (Shift-2))
  1. 9
  2. 10
  3. 8
  4. 8.5
Answer (Detailed Solution Below)
Option 1 : 9

Detailed Solution

Concept approach

A worked 4 + 3 = 7 days = 7/15; B worked 4 days = 4/10 = 6/15

⇒ together 13/15

⇒ C did 2/15 in 3 days

⇒ 40% = 2/5 = 6/15

⇒ 3 × 3 = 9 days

Ultra Calci trickLCM work

LCM 30: A = 2, B = 3

⇒ 4 days × 5 = 20

⇒ left 10 in 3 days with A + C

2 + C = 10/3

⇒ C = 4/3 per day; 40% of 30 = 12

⇒ 12 ÷ 4/3 = 9

10 ✗ 8 ✗ 8.5 ✗

⇒ 9 days