If A alone can do a work in 12 days and B alone can do it in 18 days, in how many days can they complete it together?

(SSC Selection Post 2026 (Matric, 23 Sep, Shift 3))
  1. 6 days
  2. 7.2 days
  3. 7.5 days
  4. 8 days
Answer (Detailed Solution Below)
Option 2 : 7.2 days

Detailed Solution

Concept approach

1/12 + 1/18 = 5/36

⇒ 36/5 = 7.2 days