View this question in:
A is 1.5 times as efficient as B. B takes 5 days more than A to complete the work. It is also known that B takes 3 days more than C to complete the work. All of them started the work but A left the work after 2 days from the start and C left 3 days before the completion of the work. How much time does it take to complete the work?
- 5 days
- 11 days
- 10 days
- 7 days
Answer (Detailed Solution Below)
Option 4 : 7 days
Detailed Solution
Concept approach
Times A : B = 2 : 3, difference 1 unit = 5
⇒ A = 10, B = 15, C = 12 days; work 60
⇒ A = 6, B = 4, C = 5
⇒ 6 × 2 + 4T + 5(T − 3) = 60
⇒ 9T = 63
⇒ T = 7 days
Ultra Calci trickLCM work / efficiency
A : B efficiency 3 : 2
⇒ days 2 : 3
⇒ 3u − 2u = 5
⇒ A 10, B 15 days; C = 15 − 3 = 12 days
LCM 60
⇒ efficiency A 6, B 4, C 5; total T: B works T, A works 2, C works T − 3
4T + 12 + 5(T − 3) = 60
⇒ 9T = 63
⇒ T = 7 ✓ (check: 28 + 12 + 20 = 60)
A, B की तुलना में 1.5 गुना कुशल है। B कार्य को पूरा करने में A से 5 दिन अधिक लेता है। यह भी ज्ञात है कि B कार्य को पूरा करने में C से 3 दिन अधिक लेता है। उन सभी ने कार्य करना शुरू किया लेकिन A ने शुरुआत से 2 दिन के बाद कार्य छोड़ दिया और C कार्य के पूरा होने से 3 दिन पहले छोड़ देता है। कार्य को पूरा होने में कितना समय लगता है?
- 5 दिन
- 11 दिन
- 10 दिन
- 7 दिन
उत्तर (विस्तृत हल नीचे)
विकल्प 4 : 7 दिन
विस्तृत हल
कॉन्सेप्ट से हल
A = 10, B = 15, C = 12 दिन; कार्य 60
⇒ 12 + 4T + 5(T − 3) = 60
⇒ T = 7 दिन
अल्ट्रा कैलसी ट्रिकLCM work / efficiency
A : B दक्षता 3 : 2
⇒ दिन 2 : 3
⇒ 3u − 2u = 5
⇒ A 10, B 15 दिन; C = 15 − 3 = 12 दिन
LCM 60
⇒ दक्षता A 6, B 4, C 5; कुल T: B T दिन, A 2 दिन, C (T − 3) दिन काम करता है
4T + 12 + 5(T − 3) = 60
⇒ 9T = 63
⇒ T = 7 ✓ (जाँच: 28 + 12 + 20 = 60)