Supraja and Kausalya can complete a work in 30 days and 20 days, respectively. If Supraja starts the work and they work on alternate days, in how many days will 75% of the work be completed?

(SSC CGL Tier-1 2023 (20 Jul · Shift 3 · 2:30 PM))
  1. 28
  2. 24
  3. 20
  4. 18
Answer (Detailed Solution Below)
Option 4 : 18

Detailed Solution

Concept approach

LCM 60

⇒ S = 2, K = 3

⇒ 75% = 45

⇒ 2 days = 5

⇒ 16 days = 40

⇒ left 5 = S (2) + K (3) = 2 more days

⇒ 18 days