R alone can do a work in 12 days working 4 hours a day. S alone can do the same work in 6 days working 8 hours a day. How many hours do they need to work together in a day to complete the same work in 4 days?

(SSC GD Constable 2026 (30 Apr 2026, Shift 3))
  1. 5
  2. 6
  3. 7
  4. 8
Answer (Detailed Solution Below)
Option 2 : 6

Detailed Solution

Concept approach

R: 12 × 4 = 48 h; S: 6 × 8 = 48 h

⇒ together 1/48 + 1/48 = 1/24 per hour

Total 24 h in 4 days

⇒ 6 h/day