A and B are equally efficient and each can complete a work alone in 36 days if none takes a holiday. They started together, but A took a day off after every five days of work, while B took a day off after every seven days of work. If they started on 1 July 2021, on what date was the work completed?

(SSC CPO 2023)
  1. 21 July 2021
  2. 20 July 2021
  3. 22 July 2021
  4. 19 July 2021
Answer (Detailed Solution Below)
Option 1 : 21 July 2021

Detailed Solution

Concept approach

Work = 36. A is off on days 6, 12, 18; B on day 8, 16. In 21 days A works 18 and B 19

⇒ 37 ≥ 36 (after 20 days only 17 + 18 = 35)

⇒ 21 July 2021