Jitesh and Kamal can complete a certain piece of work in 5 and 18 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?

(RRB NTPC Graduate CBT-1 2025 (19 Jun 2025, Shift 1))
  1. 11/6
  2. 25/6
  3. 7/6
  4. 13/6
Answer (Detailed Solution Below)
Option 3 : 7/6

Detailed Solution

Concept approach

Total = LCM(5, 18) = 90

⇒ Jitesh = 18, Kamal = 5 per day

3 days together = 3 × 23 = 69

⇒ left 21

Jitesh alone = 21/18

⇒ 7/6 days