6 women can do in one day the work done by 4 men in one day. A manager assigned 60 men to complete a work in 40 days, but after 25 days he realised that only 1/3 of the work was completed and decided to hire additional men to complete the remaining work in the given days. Find the number of women equal to the number of additional men employed.

  1. 180
  2. 240
  3. 200
  4. 210
Answer (Detailed Solution Below)
Option 4 : 210

Detailed Solution

Concept approach

60 × 25 = 1500 man-days = 1/3

⇒ remaining 3000 in 15 days

⇒ 200 men

⇒ additional 140 men = 140 × 3/2 = 210 women