A can complete 25% of a work in 15 days. He works for 15 days and then B alone finishes the remaining work in 30 days. In how many days will A and B working together finish 50% of the same work?

(SSC CGL Pre 2021)
  1. 25
  2. 24
  3. 20
  4. 12
Answer (Detailed Solution Below)
Option 4 : 12

Detailed Solution

Concept approach

A = 60 days; B does 75% in 30 days

⇒ 40 days. Together 1/60 + 1/40 = 1/24

⇒ 50% in 12 days

Ultra Calci trickLCM work

A: 25% in 15 days → 60 days; B: 75% in 30 days → 40 days; LCM 120 → A = 2, B = 3 per day

50% of work = 60 units → 60/(2 + 3) = 12

⇒ 25 ✗ 24 ✗ 20 ✗

⇒ 12 ✓