Selection KeySelection KeyFree Mock Test
View this question in:

A, B and C can complete a work in 4, 8 and 16 days respectively. They work on alternate days — A on the first day, B on the second, C on the third, A on the fourth and so on. Find the number of days in which 175% of the work is done.

  1. 11 days
  2. 9 days
  3. 12 days
  4. 5 days
Answer (Detailed Solution Below)
Option 3 : 12 days

Detailed Solution

Concept approach

Work 16: A = 4, B = 2, C = 1

⇒ 3 days = 7; 175% = 28 = 4 cycles

⇒ 12 days