10 men and 15 women can complete a project in 12 days. If after 8 days, only 2/3 of the work is completed, how many more women must be added to finish the work in the next 2 days, assuming all men continue?

(RRB NTPC Undergraduate CBT-1 2026 (17 Jun 2026, Shift 2))
  1. 20
  2. 25
  3. 30
  4. 35
Answer (Detailed Solution Below)
Option 2 : 25

Detailed Solution

Concept approach

8 days of 12

⇒ 2/3 done as planned; left 1/3 in 2 days

Group does 1/12 per day, needed 1/6 per day

⇒ twice the group

Extra = 10 men + 15 women = 25 persons (man = woman taken)

⇒ 25