A man can finish a work in 10 days and a woman can finish it in 12 days. In how many days will the work be finished by a man and a woman working together every day?

(SSC CGL Pre 2023)
  1. 60/11
  2. 61/10
  3. 31/10
  4. 30/10
Answer (Detailed Solution Below)
Option 1 : 60/11

Detailed Solution

Concept approach

1/10 + 1/12 = 11/60

⇒ 60/11 days