A can complete a certain work alone in 10 days, while B can complete the same work in 5 days. They work together for 2 days, after which B leaves and C joins A. A and C then complete the remaining work in 3 days. Find the number of days C would take to complete 40% of the work if working alone.

(SSC CGL 2026 (6 Oct, Shift 2))
  1. 8 days
  2. 10 days
  3. 12 days
  4. 16 days
Answer (Detailed Solution Below)
Option 3 : 12 days

Detailed Solution

Concept approach

LCM 10: A = 1, B = 2 per day. Together 2 days = 6

⇒ left 4

A + C do 4 in 3 days

⇒ 4/3 per day

⇒ C = 1/3 per day

C alone: 30 days

⇒ 40% work = 12 days

Ultra Calci trickLCM work / efficiency

Total work = LCM(10, 5) × 3 = 30 units

⇒ A = 3, B = 6 per day

2 days (A+B) = 2 × 9 = 18

⇒ left 12 in 3 days

⇒ A + C = 4

⇒ C = 1 per day

40% of 30 = 12 units

⇒ 12 ÷ 1 = 12 days ✓