A, B and C can do a work separately in 18, 36 and 54 days, respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?

(SSC CGL Mains 2019 (18 Nov 2020))
  1. 12 days
  2. 13 days
  3. 15 days
  4. 14 days
Answer (Detailed Solution Below)
Option 2 : 13 days

Detailed Solution

Concept approach

LCM 108: A = 6, B = 3, C = 2 per day; total days T

6T + 3(T − 5) + 2(T − 10) = 108

⇒ 11T = 143

⇒ T = 13 days

Ultra Calci trickLCM work

LCM 108: A = 6, B = 3, C = 2 per day; T = total days → B works T − 5, C works T − 10

6T + 3(T − 5) + 2(T − 10) = 108 → 11T = 143 → T = 13 (143 = 11 × 13)

12 ✗ 15 ✗ 14 ✗

⇒ 13 days ✓