A started a work and left after working for 3 days; then B was called and he finished the work in 6 days. If A had left after working for 2 days, B would have finished the remaining work in 9 days. In how many days can A and B working together finish the whole work?

  1. 15/4
  2. 4
  3. 3
  4. 5
Answer (Detailed Solution Below)
Option 1 : 15/4

Detailed Solution

Concept approach

A × 1 = B × 3

⇒ A = 3, B = 1

⇒ work = 3 × 3 + 6 × 1 = 15

⇒ together 15/4 days

Ultra Calci trickefficiency equation

3A + 6B = 2A + 9B → A = 3B

Work = 3A + 6B = 15B → together A + B = 4B per day

⇒ 15/4 days ✓