A man, a boy and a woman can finish a work in 10 days, 15 days and 30 days, respectively. In how many days can the work be finished by a man, a woman and a boy when all of them work together?

(SSC CGL Tier-1 2023 (14 Jul · Shift 1 · 9:00 AM))
  1. 10
  2. 5
  3. 8
  4. 6
Answer (Detailed Solution Below)
Option 2 : 5

Detailed Solution

Concept approach

Man + boy + woman = 1/10 + 1/15 + 1/30 = (3 + 2 + 1)/30 = 1/5

⇒ 5 days