A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can A working alone complete 60% of the work?

(SSC CGL Tier-1 2022 (2 Dec · Shift 4 · 5:15 PM))
  1. 70
  2. 110
  3. 80
  4. 105
Answer (Detailed Solution Below)
Option 3 : 80

Detailed Solution

Concept approach

A : B efficiency = 60 : 100 = 3 : 5

⇒ total work = 8 × 50 = 400

⇒ 60% = 240

⇒ 240 ÷ 3 = 80 days