A can complete a piece of work in 14 days and B can complete it in 10 days. If they work on alternate days, starting with B on the first day, then in how many days will the work be finished?

(RRB NTPC Graduate CBT-1 2025 (13 Jun 2025, Shift 1))
  1. 11⅔
  2. 10⅔
  3. 11⅗
  4. 10⅗
Answer (Detailed Solution Below)
Option 3 : 11⅗

Detailed Solution

Concept approach

Total = LCM(14, 10) = 70

⇒ A = 5, B = 7 per day

⇒ pair = 12

5 pairs = 10 days = 60

⇒ left 10

Day 11: B does 7, left 3

⇒ A needs 3/5 day

⇒ 11 3/5 days