A takes twice as much time as B and thrice as much time as C to finalise a task.
Working together, they can complete the task in 8 days. The time (in days) taken by A, B and C, respectively, to complete the task is:

(SSC CGL Tier-1 2022 (2 Dec · Shift 2 · 11:45 AM))
  1. 42, 21, 14
  2. 60, 30, 20
  3. 54, 27, 18
  4. 48, 24, 16
Answer (Detailed Solution Below)
Option 4 : 48, 24, 16

Detailed Solution

Concept approach

A : B : C time = 6 : 3 : 2

⇒ rates 1 + 2 + 3 = 6 per 6k

⇒ together k = 8

⇒ 48, 24, 16