If 5 workers can complete of a work in 12 3
days, how many workers are needed to complete the full work in 15 days?

(SSC Selection Post 2026 (Matric, 19 Sep, Shift 3))
  1. 5
  2. 6
  3. 7
  4. 8
Answer (Detailed Solution Below)
Option 2 : 6

Detailed Solution

Concept approach

5 workers do 2/3 work in 12 days

⇒ full work = 5 × 12 × 3/2 = 90 worker-days

⇒ 90 ÷ 15 = 6 workers