Selection KeySelection KeyFree Mock Test
View this question in:

A and B together can complete a certain work in 54 days. They work together for 12 days. The remaining work was completed by A, B and C together in 28 days. If the work done by B in 6 days is equal to the work done by C in 9 days, then A alone can complete two-thirds of the work in how many days?

(IB ACIO Tier-1 2023)
  1. 108
  2. 144
  3. 180
  4. 216
Answer (Detailed Solution Below)
Option 2 : 144

Detailed Solution

Concept approach

Remaining 42/54 by A+B+C in 28 days

⇒ (A+B)·42 = (A+B+C)·28

⇒ A+B : A+B+C = 2 : 3

⇒ C = ½(A+B). B : C = 3 : 2. Take A+B = 2

⇒ C = 1, B = 1.5, A = 0.5; work = 2 × 54 = 108

⇒ A for 2/3 = 72/0.5 = 144 days

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →