A group of men committed to completing a task in 20 days. The work was completed in 40 days because 5 workers did not come for work. Determine the number of men who originally agreed to do the work.

(SSC CPO Paper-1 2022 (11 Nov 2022, Shift 1))
  1. 15
  2. 10
  3. 12
  4. 18
Answer (Detailed Solution Below)
Option 2 : 10

Detailed Solution

Concept approach

Original men n

⇒ 20n = 40(n − 5)

20n = 200

⇒ n = 10