Amar can complete a work in 15 days and Prem in 12 days. Starting with Amar, they work on alternate days. In how many days will the work be completed?

(SSC CGL 18.07.2023)
  1. 13 2/5
  2. 12 1/6
  3. 13 1/2
  4. 13
Answer (Detailed Solution Below)
Option 1 : 13 2/5

Detailed Solution

Concept approach

Total = 60; Amar 4, Prem 5

⇒ 9 per 2 days. 12 days = 54; day 13 Amar 4

⇒ 2 left; day 14 Prem 2/5 day

⇒ 13 2/5 days