A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:

(SSC CGL Tier-1 2025 (15 Sep · Shift 2 · 12:30 PM))
  1. 19.2 days
  2. 22.5 days
  3. 16 days
  4. 20 days
Answer (Detailed Solution Below)
Option 2 : 22.5 days

Detailed Solution

Concept approach

A is 3 times as efficient

⇒ time A : B = 1 : 3

2 units = 60 days

⇒ A = 30, B = 90

⇒ together = 30 × 90/120 = 22.5 days