5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?

(SSC CHSL 2020 (13 Oct 2020, Shift 1))
  1. 72
  2. 56
  3. 64
  4. 36
Answer (Detailed Solution Below)
Option 2 : 56

Detailed Solution

Concept approach

34(5m + 8w) = 28(4m + 18w)

⇒ 170m + 272w = 112m + 504w

⇒ m = 4w

Total work = 34 × (20w + 8w) = 952w

3m + 5w = 17w

⇒ 952/17 = 56 days