Forty workers working 6 hours a day complete one-fifth of a work in the first 7 days. Work then stops completely for 3 days. When work resumes, only 28 of the original workers return. Every returning or newly added worker is 25% more efficient than during the first stage and works 8 hours a day. How many new workers must be added so that the work is completed by the original 22-day deadline?
(SSC CGL 2026 (22 Oct, Shift 3))
- 24 workers
- 26 workers
- 28 workers
- 30 workers
Answer (Detailed Solution Below)
Option 3 : 28 workers
Detailed Solution
Concept approach
Work in first stage = 40×6×7 = 1680 man-hr = 1/5
⇒ total 8400, left 6720. Days left = 22 − 7 − 3 = 12. New output/worker/day = 8×1.25 = 10
⇒ need 6720/12 = 560/day
⇒ 56 workers. 56 − 28 = 28 new workers.
प्रतिदिन 6 घंटे काम करने वाले चालीस श्रमिक पहले 7 दिनों में काम का पाँचवाँ भाग पूरा करते हैं। फिर काम 3 दिनों के लिए पूरी तरह रुक जाता है। जब काम फिर शुरू होता है, तो मूल श्रमिकों में से केवल 28 वापस आते हैं। लौटने वाला या नया जोड़ा गया प्रत्येक श्रमिक पहले चरण की तुलना में 25% अधिक दक्ष है और प्रतिदिन 8 घंटे काम करता है। मूल 22-दिन की समय सीमा तक काम पूरा करने के लिए कितने नए श्रमिक जोड़ने होंगे?
(SSC CGL 2026 (22 Oct, Shift 3))
- 24 श्रमिक
- 26 श्रमिक
- 28 श्रमिक
- 30 श्रमिक
उत्तर (विस्तृत हल नीचे)
विकल्प 3 : 28 श्रमिक
विस्तृत हल
कॉन्सेप्ट से हल
पहले चरण में कार्य = 40×6×7 = 1680 man-hr = 1/5
⇒ कुल 8400, शेष 6720। बचे दिन = 22 − 7 − 3 = 12। नया कार्य/कर्मचारी/दिन = 8×1.25 = 10
⇒ चाहिए 6720/12 = 560/दिन
⇒ 56 कर्मचारी। 56 − 28 = 28 नए कर्मचारी।