Forty workers working 6 hours a day complete one-fifth of a work in the first 7 days. Work then stops completely for 3 days. When work resumes, only 28 of the original workers return. Every returning or newly added worker is 25% more efficient than during the first stage and works 8 hours a day. How many new workers must be added so that the work is completed by the original 22-day deadline?

(SSC CGL 2026 (22 Oct, Shift 3))
  1. 24 workers
  2. 26 workers
  3. 28 workers
  4. 30 workers
Answer (Detailed Solution Below)
Option 3 : 28 workers

Detailed Solution

Concept approach

Work in first stage = 40×6×7 = 1680 man-hr = 1/5

⇒ total 8400, left 6720. Days left = 22 − 7 − 3 = 12. New output/worker/day = 8×1.25 = 10

⇒ need 6720/12 = 560/day

⇒ 56 workers. 56 − 28 = 28 new workers.