A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that, C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone?

(SSC CGL Mains 2016 (30.11.2017))
  1. 30 days
  2. 50 days
  3. 40 days
  4. 60 days
Answer (Detailed Solution Below)
Option 3 : 40 days

Detailed Solution

Concept approach

Total = 60; A 6, B 5. 3 days = 33; A 2 days = 12

⇒ 45; last 2 days (A + C) = 15

⇒ A + C = 7.5

⇒ C = 1.5

⇒ 40 days