A, B and C can do a piece of work in 20 days, 30 days and 60 days respectively. If A works daily and on every third day B and C also work with A, then in how many days, will the work be completed?

(SSC CPO Paper-1 2023 (03 Oct 2023, Shift 1))
  1. 21
  2. 18
  3. 12
  4. 15
Answer (Detailed Solution Below)
Option 4 : 15

Detailed Solution

Concept approach

LCM(20, 30, 60) = 60

⇒ A = 3, B = 2, C = 1

3 days: 3 + 3 + (3 + 2 + 1) = 12

60/12 = 5 cycles

⇒ 15 days