'A' alone can do a piece of work in 10 days and 'B' alone can do it in 15 days. 'A' and 'B' undertook to do the work for Rs 42,000. With the help of 'C', they completed the work in 5 days. How much is to be paid to C?

(SSC MTS 2020)
  1. 7,000
  2. 15,000
  3. 14,000
  4. 21,000
Answer (Detailed Solution Below)
Option 1 : 7,000

Detailed Solution

Concept approach

5 days: A = 1/2, B = 1/3

⇒ C = 1/6

⇒ 42000/6 = Rs 7,000