Selection KeySelection KeyFree Mock Test
View this question in:

36 equally efficient workers can paint 25 identical walls in 48 days. In how many days can 45 such workers paint 60 such walls?

(SSC CPO Paper-1 2023 (04 Oct 2023, Shift 3))
  1. 92.36
  2. 92.16
  3. 91.96
  4. 91.16
Answer (Detailed Solution Below)
Option 2 : 92.16

Detailed Solution

Concept approach

Man-days per wall = 36 × 48/25 = 69.12

60 walls = 4147.2 man-days

days = 4147.2/45 = 92.16

Ultra Calci trickd.s (cancel before d.s)

Days = 48 × 36/45 × 60/25 → cancel 36/45 = 4/5 → 48 × 4 × 12/25 = 2304/25

d.s: 2304 → 0 → answer d.s 0

92.36 (2) ✗ 91.96 (7) ✗ 91.16 (8) ✗ 92.16 (0) ✓

⇒ 92.16

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →