To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in 11 1/3 days, then B alone can complete 7/9 part of the original work in:

(SSC CGL 2020)
  1. 5 1/2 days
  2. 4 days
  3. 4 1/2 days
  4. 6 days
Answer (Detailed Solution Below)
Option 4 : 6 days

Detailed Solution

Concept approach

B works 6 days, A works 5 1/3 days

⇒ A does (16/3)/24 = 2/9

⇒ B does 7/9 in 6 days