A, B and C can do a piece of work in 9 days, 12 days and 18 days respectively. A started the work and worked for 3 days and left. Then, B joined the work and worked for 3 days and left. Then, C joined the work and completed the work. Find how many days C took to complete the work.

(Selection Post Phase XII (2024))
  1. 7
  2. 7 1/2
  3. 8 1/2
  4. 8
Answer (Detailed Solution Below)
Option 2 : 7 1/2

Detailed Solution

Concept approach

A did 3/9 = 1/3, B did 3/12 = 1/4

⇒ remaining 5/12

⇒ C takes 5/12 × 18 = 7½ days