A can finish 30% of a task in 9 days, B can complete 2/5 of the same task in 10 days, C can do 1/6 of it in 5 days, and D can complete 50% of the task in 12 days. Who among them is the fastest to complete the entire work individually?

(SSC CGL 2026 (27 Oct, Shift 3))
  1. A
  2. B
  3. C
  4. D
Answer (Detailed Solution Below)
Option 4 : D

Detailed Solution

Concept approach

Full work: A = 9/0.3 = 30 days, B = 10/(2/5) = 25 days, C = 5×6 = 30 days, D = 12/0.5 = 24 days

⇒ D is fastest.

Ultra Calci trickwork units

Whole work: A 9 × 10/3 = 30 days; B 10 × 5/2 = 25; C 5 × 6 = 30; D 12 × 2 = 24

Least days = fastest

⇒ D ✓