Selection KeySelection KeyFree Mock Test
View this question in:

A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in:

(SSC CGL Mains 2018 (12.09.2019))
  1. 2 1/2 days
  2. 3 days
  3. 1 1/2 days
  4. 2 days
Answer (Detailed Solution Below)
Option 4 : 2 days

Detailed Solution

Concept approach

A = 30 days, B = 25 days. Total = 150: A 5, B 6. 10 days = 110

⇒ C does 40 in 4 days

⇒ C = 10. A+B+C = 21; 28% of 150 = 42

⇒ 2 days

Ultra Calci trickLCM work

A: 100% in 30 days, B: 25 days → work 150: A 5, B 6 per day

10 days → 110, left 40 by C in 4 days → C = 10 → A + B + C = 21/day

28% of 150 = 42 → 42/21

⇒ 2 days ✓