‘A’ can complete the 60% of the work in 9 days, while ‘B’ can complete the work in 7½ days. If they work together, then in how many days will the work be completed?

(SSC MTS 2021 (26 Oct 2021, Shift 1))
  1. 7
  2. 6
  3. 5
  4. 4
Answer (Detailed Solution Below)
Option 3 : 5

Detailed Solution

Concept approach

A: 60% in 9 days

⇒ 100% in 15 days; B alone = 7.5 days

Work 15: A = 1, B = 2

⇒ 3/day

⇒ 15/3 = 5 days

⇒ option C