A can complete a task in 15 days, and B can complete the same task in 20 days. How long will it take them to complete the task together?

(SSC CGL Tier-1 2025 (25 Sep · Shift 2 · 12:30 PM))
  1. 5.5 days
  2. 6.5 days
  3. 7.5 days
  4. 8.5 days
Answer (Detailed Solution Below)
Option 4 : 8.5 days

Detailed Solution

Concept approach

LCM 60

⇒ eff A = 4, B = 3

⇒ total 7

Days = 60/7 = 8.57 ≈ 8.5 days