A certain number of persons can complete a work in 90 days. If there were 10 persons less, it would have taken 10 days more. Find the number of persons in the beginning.

(SSC CHSL 2022)
  1. 100
  2. 85
  3. 90
  4. 110
Answer (Detailed Solution Below)
Option 1 : 100

Detailed Solution

Concept approach

Days 90 : 100

⇒ persons 10 : 9

⇒ difference 1 part = 10

⇒ 100 persons