A and B can complete a task in 12 days and 18 days, respectively. They begin the work together, but B leaves after 4 days. How many more days will A take to finish the remaining work?

(SSC CGL Tier-1 2025 (15 Sep · Shift 3 · 4:00 PM))
  1. 5⅓ days
  2. 2¾ days
  3. 1⅕ days
  4. 8⁶⁄₇ days
Answer (Detailed Solution Below)
Option 1 : 5⅓ days

Detailed Solution

Concept approach

Efficiency: A = 3, B = 2 (LCM 36)

4 days together = 5 × 4 = 20

⇒ left 16

A alone = 16/3 = 5⅓ days (option A '53 days' = 5⅓ days)