Ratnesh and Vineet worked on alternate days, starting with Ratnesh. The entire work got completed in 54 3/4 days. If Ratnesh alone can finish the work in 48 days, then in how many days can Vineet alone do the work?

(SSC CHSL Mains 2024)
  1. 66
  2. 64
  3. 60
  4. 62
Answer (Detailed Solution Below)
Option 2 : 64

Detailed Solution

Concept approach

In 54 3/4 days Ratnesh works 27 + 3/4 = 27.75 days, Vineet 27 days. Ratnesh's share = 27.75/48

⇒ Vineet did 20.25/48 in 27 days

⇒ Vineet alone = 27 × 48/20.25 = 64 days