Sanjay and Rohan can complete a work in 8 days and 12 days, respectively. Starting with Sanjay, they work on alternate days. In how many days will the work be completed?

(SSC CPO Paper-1 2023 (04 Oct 2023, Shift 3))
  1. 8½
  2. 9½
  3. 9⅔
  4. 9⅓
Answer (Detailed Solution Below)
Option 2 : 9½

Detailed Solution

Concept approach

LCM 24: Sanjay 3/day, Rohan 2/day

⇒ 5 per 2 days. 8 days = 20; day 9 Sanjay = 23; remaining 1 unit by Rohan = 1/2 day

⇒ 9½ days

⇒ option B.