20 men can dig a 30 m long ditch in 22 days working 6 hours/day. How many men will dig a 59 m long ditch in 11 days working 8 hours/day?

  1. 30
  2. 59
  3. 60
  4. 55
Answer (Detailed Solution Below)
Option 2 : 59

Detailed Solution

Concept approach

20 × 22 × 6/30 = M × 11 × 8/59

⇒ M = 20 × 22 × 6 × 59/(30 × 88) = 59

Ultra Calci trickmultiple-of-59

Men = 20 × 59/30 × 22/11 × 6/8 → 59 is prime and no denominator cancels it → multiple of 59

30 ✗ 60 ✗ 55 ✗ 59 ✓

⇒ 59 men