X and Z start a piece of work and after 12 days Z left the work. 4 days after Z left the work, Y joined X and they finished the whole work in 'T' days. Each person did an equal share of the work. If X and Z had worked together, the work would have ended in 'T' days. Find in how many days Y alone can complete the work.

  1. 24 days
  2. 20 days
  3. 15 days
  4. 30 days
Answer (Detailed Solution Below)
Option 1 : 24 days

Detailed Solution

Concept approach

Each did 1/3. X: 1/3 in T days; Z: 1/3 in 12 days

⇒ in T days Z does 2/3 (X+Z for T days = 1/3 + 2/3 = 1)

⇒ T = 24 days. Y joined on day 16

⇒ worked 24 − 16 = 8 days = 1/3

⇒ Y alone = 24 days